Logistics Planning for Critical Machine Parts in Cement Manufacturing
DOI:
https://doi.org/10.25077/inomet.3.1.36-43.2025Keywords:
Inventory Planning, Safety Stock, Reorder PointAbstract
This study aims to determine the optimal safety stock and reorder point for bearing spare parts at the PT. XYZ warehouse to reduce the risk of stockouts and ensure production continuity. Forecasting was conducted using five methods: exponential smoothing, Holt-Winters, moving average, exponential trend, and seasonal naive. Forecast accuracy evaluation using MAPE, MAD, MSE, and SSE metrics shows that the moving average method was the most suitable for the dataset. Based on the forecast results and considering a 99% service level, the calculated safety stock is 47 units, and the reorder point is 977 units. The sensitivity analysis conducted in this study demonstrates the significant impact of demand and lead time variation on reorder point and safety stock. The analysis further shows that under different scenarios, the reorder point can vary considerably, ranging from 686 to 939 units at an 8-day lead time. Compared to a benchmark calculation for a 99% service level, the proposed values offer a more conservative and resilient buffer, particularly for critical components such as bearings.
Downloads
Published
Issue
Section
License
Copyright (c) 2025 Jurnal Inovasi Rekayasa Mekanikal dan Termal

This work is licensed under a Creative Commons Attribution-NonCommercial-ShareAlike 4.0 International License.